Queries on CN25 Transaction

Former Member
0 Kudos

Hi Guru's

Please address my Queries on CN25 Transaction at the earliest :-

(1) Is it possible to add new items to a reservation material even after items have already been consumed against it by doing goods movement ?

(2) Once material has been consumed doing CN25 transaction for a reservation material, is it possible to reverse the complete transaction ?

(3) What is the transaction code to view the materials attached to a particular resevation material once it is consumed ( Goods movement is done ) ?

Regards,

Sai

Edited by: Julius Bussche on Sep 24, 2009 1:35 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

(1) Is it possible to add new items to a reservation material even after items have already been consumed against it by doing goods movement ?

Yes it is possible, but this practice is not advisable to do in SAP system. If you follow this process the data inconsistency will happen.

Once material has been consumed doing CN25 transaction for a reservation material, is it possible to reverse the complete transaction ?

For this you need to carry out two steps

1. Cancel the Network confirmation using CN29

2. Cancel the material documents using MIGO

) What is the transaction code to view the materials attached to a particular reservation material once it is consumed ( Goods movement is done ) ?

MB23 and MB25

Thanks

S.Murali