Skip to Content
avatar image
Former Member

BC Sets Workflow

Hi all,

I am using SRM 7.0 and activated BC Set for One Step approval manager for RFX (/SAPSRM/C_RQ_600_001_SP04) in transaction SCPR20.

Now for testing reasons I would like to activate the BC Set for RFX Without approval (/SAPSRM/C_RQ_600_000_SP04).

What is the process to change from one BC Set to another? just have to activate the second one?

Or need to deactivate the first BC Set first?

Thanks,

Ezequiel

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Sep 24, 2009 at 06:38 AM

    Hi

    you have to deactivate the First one( One Step approval manager) and

    Activate the New workflow.(RFX Without approval )

    normally two workflow should not be active. it will lead to an error called "Workflow is ambigous"

    Regards

    G.Ganesh kumar

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 24, 2009 at 03:39 AM

    Hi,

    Just activate the second one.

    Regards,

    Masa

    Add comment