cancel
Showing results for 
Search instead for 
Did you mean: 

Sales order stock with Project

Former Member
0 Kudos

Hi Gurus,

We have a scenario where we prepares a project when we receive the inquire for product development. Following are the steps of activities :

1. Create a project & WBS elements with "No project stock" indicator.

2. Prepare the cost planning with ref to Primary Cost Elements & unit costing.

3. Release the budget.

4. Create sales order with reference to WBS element.

5. (Acct. Assignment category is D with special Stock E & consumption P)

6. Carryout MRP run.

7. Convert PR into PO & do Goods Receipt.

8. Consumption of Mat into Production order and GR of Finish product.

Problems : In case of Acct. Ass. Cat. D when we do the good receipt against Pur. Order, system updates qty but not the value... cost is directly posted to project. Project actual cost is updated but in case when we want to use the same material available in stock to another project what should be done as there is no inventory value.

The special stock indicator is needed to control the flow of material. Stock must be valuated as sometimes needs to transfer to other order. All the cost needs to be captured against the Project for the comparison against planned cost. we also need to control the budget not only on the released value but also based on the unit costing in cost planning. i.e. material, qty and value has been maintained in cost planning. Purch. Order / Prod. Order value for the particular material should not exceed the details in cost planning.

Kindly advise what is the best possible solution to the requirement.

Regards,

SAP IS FUN :?)

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

If the value flow for project stock needs to be seen then you need to select valuated project stock while creation of the project at project definition or make make it default at project profile level.

Secondly with reference to Purchase order, you can use account assignment Q which will update price as well as quantity to the respective WBS element as a part special stock.

And Budget always works in reference to the commitment value and not the planned value, if I am not wrong.

I hope this would help you.

Regards

Avisek Bhardwaj

Former Member
0 Kudos

Thank you Avisek,

My problem is i am using IS-AFS, which does not allow AFS material to assign to project in such cases what should be my configuration for the acct. assgn. cat. for the SD part.

Regards,

SAP IS FUN

Former Member
0 Kudos

Hi,

If your project is based on sale order then, through OVZG, OVZH and assignment to transaction maintain special stock as sale order stock, and for project use network header assigned network type.

I hope this should help you.

Regards

Avisek Bhardwaj

Answers (0)