Pl. tell me what can be the typical questions asked to the client to Pre Upgrade assessment of SAP ECC 6.0

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

The questions can be like the following -

  1. Modules implemented

  2. Interfaces Connected, mode of communication

  3. Database Size

  4. Code Pages Installed

  5. OS and DB Versions

  6. GUI Version

  7. Patch Levels

  8. Downtime window that is available for Upgrade

  9. Dependency on any parallel projects for Upgrade

  10. Whether ITS is installed

  11. Hardware availability for Upgrade

..................