Dear experts,
I check PR table (EBAN) and I found 2 fields : BADAT and ERDAT.
Do you know about difference between EBAN-BADAT and EBAN-ERDAT?
Please help.
Best regards
Anita A.
BADAT - Request Date - it would be any date compared to system date
ERDAT - Date on which the PR was created
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Mr G Lakshmipathi,
Thanks for your respon.
Can you help me to explain about BADAT calculation ?
Because after I run MPS at 26.09.2018 and PR was created.
BADAT from that PR is 26.07.2018 ( 2 months before MPS run).
Notes = MPS run always refer to current date and it can't be changed manually.
Thanks
Best regards
Anita