Dear experts,

I check PR table (EBAN) and I found 2 fields : BADAT and ERDAT.

Do you know about difference between EBAN-BADAT and EBAN-ERDAT?

Please help.


Best regards

Anita A.

Accepted Solutions (0)

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

BADAT - Request Date - it would be any date compared to system date

ERDAT - Date on which the PR was created

anitaarifin04
Participant
0 Kudos

Dear Mr G Lakshmipathi,

Thanks for your respon.

Can you help me to explain about BADAT calculation ?

Because after I run MPS at 26.09.2018 and PR was created.

BADAT from that PR is 26.07.2018 ( 2 months before MPS run).

Notes = MPS run always refer to current date and it can't be changed manually.

Thanks

Best regards

Anita