Creating deliveries from purchase order -Plant to plant process

Former Member
0 Kudos

Hi All,

I am carying out delivery creation in P2P process from a purchase order . There are two bill to parties assigned in customer. When i create delivery for first bill to party , system creates only one delivery for all line items . But supposed i create delivery for second bill to partyy , the system creates diferent deliveries for each line item . It gives message as delivery split because the partners are different . Can anybody help me why this is hapening .

Note : i have already maintained "order combination tick " in customer master and also in PO line item level .

Thankls

Rohit Chavan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Check for the properties for the order combination like ship-to-party, Route and etc.

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks

Former Member
0 Kudos

Just check in the Second Bill-to party the following points as per the Line Items:-

1. Shipping point

2. Route

3. Ship-to Party

4. Incoterms

If the above mentioned are different,then delivery will be splitted into many Deliveries.

Best regards,

Ankur