Dear experts,

I want to change PR request date/creation date.

PR automatically created by MPS run (Tcode MD40).

How to change PR request/creation date?

Thanks

Best regards

Anita A.

Accepted Solutions (0)

Answers (4)

Answers (4)

anitaarifin04
Participant
0 Kudos

Dear all,

we can change request date of Purchase Requsition with solution ME_UPDATE_REQUISITION



Thanks and regards

Anita A.

Prasath
Contributor
0 Kudos

Hi Anitha,

PR Creation and requisition date obviously generated by System only i.e MPS/MRP run date. You cannot do any more changes on the same. May I know business requirement to change those dates.

Regards,

Prasath E

anitaarifin04
Participant

Dear Mr.Prasath E,

Thanks for help

Regards

Anita

ankurch
Active Contributor
0 Kudos

HI Anita,

You can not change creation date as it will become non-editable once you PR number generate! alternatively you can delete that PR and create a new where you can make changes!

Thanks,

anitaarifin04
Participant
0 Kudos

Dear Mr.Ankur Chauhan,

Thanks for help

Regards

Anita

anilmalhotra88
Participant
0 Kudos

Hi Anita,

The requisition date will be set by the system & cannot be changed. The requisition date can be set during creation in ME51N screen in item details under Quantity/Dates tab, before finishing the line item data, once all the data for line item data is entered the field will become non-editable.

Regards,

Anil Malhotra

anitaarifin04
Participant
0 Kudos

Dear Mr. Anil Malhotra,

Thanks for help

Regards

Anita