Acct. assign. cat. "P" for purchase req. Project stock does not exist.

Hello All,

I am trying to give Account assignment category Projects as " P" to the Document type NB in OPTT (Account assignment categories for order) configuration.

System give the error message " Acct. assign. cat. "P" for purchase req. Project stock does not exist."

Please help me with this , thanks in advance.

Thanks,

Srihari.G

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Sep 22, 2009 at 06:36 AM

    Hi,

    Step1: SPRO>PS>Material>Control of Sales order related Production>Check Account assignment Categories

    Step2: Select P (Project) and In the special stock Mention Q and Save.

    Step3: Tcode OPTT will allow to change to P.

    Hope it helps...