Former Member

Person responsible

Hi

When a new WBS is been added below the parent WBS - person responsible is automatically copied from the parent WBS in the new WBS which being created.

Tried by creating the substitution rule but not working . Means this rule should be substituated at any level when a new WBS is being created - means "whenever a new WBS is been added - person responsible field should be empty and it should not be copied from its parents wbs"

Prerequisite :-

PRPS-STUFE = '' " AND

PRPS-VERNR = '' "

Substitution:

Field - RCJ_PRPSUP-VERNA

hope an possible answer for this query.

Thnx

PP

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 22, 2009 at 09:52 AM

    Hi,

    in our system, when i create a WBS element under a parent one, it doesn't copy the person responsible.....

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi

      If you have not maintained then yes the NEW WBS will not have the person responsible. If you have maintained then it will copy the person responsible also.

      Can anyone help me on the query.

      Regards

      PP

  • avatar image
    Former Member
    Sep 24, 2009 at 06:14 AM

    Hi,

    When a new WBS element is created at any level it copies person responsible from project definition.

    Try your substitution using project definition fields...

    Regards!