Dear Experts,

I have the following requirement:

Project A has 50 activities. Completion of first 10 activities symbolizes 20% of completion of the total Project A.

Is there is away to track Project progress in this manner?

What are the available report?

Can we use "Percentage of Completion" option in Milestones to cater this requirement?

Your guidance is greatly appreciated,

Dileepa.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Sep 22, 2009 at 06:59 AM

    Hi,

    Use the POC weight field in the Progress Tab of the Activity.

    Hope it helps...

    Thanks!!!

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 22, 2009 at 12:21 PM

    Hi

    You can Use POC weight field for Network Activities/WBSE to capture Project Progress interms of % age.

    Again various reports are available for Project Progress analysis. Like Progress analysis Workbench, Progress Analysis Report

    Swapnil Kharul

    Add comment