Hello SAP Gurus!

We are having a problem regarding PR creation.

No PR is created after running MRP and we have a lot of requirements.

What do you think is the problem?

How to check?

Thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Related questions

6 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Sep 19, 2009 at 05:58 AM

    Dear Friend,

    Check the following things

    1. raw material is maintained for MRP views or not check,

    2. if in the MRP you selected MRP type As ND at the time also it will not recognize the material

    Regards

    Pramod

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 19, 2009 at 06:00 AM

    Hi,

    Check Whether ur MRP Grp is set to Create PR or not.

    SPRO --> MM --> consumption Based Planning --> MRP Grp --> Carry out over all maintenance for MRP Grp -->

    Here Give the name of the Plant and also MRP Grp(000 External procurement)

    Check here PR requestion '1' is maintained or not.

    Hope Help u !

    Regards,

    pardeep malik

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 19, 2009 at 11:47 AM

    Check concern item through md04. if old purchase order / purchase requisition may open.

    check procurement type in mrp screen. it should be F

    Vijay

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 19, 2009 at 06:11 PM

    Hi,

    Kindly check these 3 steps below for you

    1) Requirement Planning for the corresponding plant must be activated in customizing for material management under consumption based planning -


    >Planning------>Activate Material Requirement Planning

    2)The Plant parameters for the corresponding plant must be activated in customizing for material management under consumption based planning->Plant Parameters-->Carryout overall maintenance of plant parameters

    3) In the material master record, you have to maintain the MRP data of the materials that are subject to automatic plannning

    Viz , MRP TYPE, MRP GROUP...Etc

    Thanks

    Tushar Patankar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 21, 2009 at 05:30 AM

    Dear Nanz,

    What i think is you should check the stock first....It must not have gone below ROP, so might be its 1 of the reason its not generating PR....M talking abt CBP...

    Regards

    Nainesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 21, 2009 at 06:37 AM

    Hi again,

    Kindly let me know have you check these 3 steps below for you

    1) Requirement Planning for the corresponding plant must be activated in customizing for material management under consumption based planning -


    >Planning------>Activate Material Requirement Planning

    2)The Plant parameters for the corresponding plant must be activated in customizing for material management under consumption based planning->Plant Parameters-->Carryout overall maintenance of plant parameters

    3) In the material master record, you have to maintain the MRP data of the materials that are subject to automatic plannning

    Viz , MRP TYPE, MRP GROUP...Etc

    If tthe above steps are ok then check the material master record of material of which MRP run is resulting in no Purchase requistion, Kindly check the MRP Views and see whether field of MRP Type is showing ND i.e. No Planning.

    Change the same to consumption based planning and get your reults.

    I hope this will solve your problem.

    Regards,

    Tushar Patankar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.