Hi All,

I want to know if it is possible to change the number of individual capacity per day or per week. When we know there will be an increase of labor (more people), change the capacity for that week so that we know where we stand.

When we change it now, the capacity is changed for everything.

Is it possible to modify it per day, or per week? If so, in what transaction is that? The same as what I am using now (CR02)? And will it be possible to see it in the CM21 transaction when we dispatch it?

Thank you for your answer!

Best regards

Manuel

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

In the work center capacity header, you should click the button "Intervals and Shifts". Here, you will be able to create different intervals of available capacity and define the number of capacities in each interval.

Please observe that you will also have to input the Active Version number in the respective field of the capacity header, since you may have different versions of available capacity.

Regards,

Caetano