Skip to Content
author's profile photo Former Member
Former Member

How to enter material in the Activities.

We have to enter materials in the 300 activities --different materials.

How can we achieve automation the process instead of attaching the materials manually to the activities in the system.

regards,

Amlan Sarkar

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

6 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2009 at 06:16 AM

    Hi

    You can go through standard process of assigning the material components through BOM transfer program in tcode CN33 or use a program to upload the materials. You can choose BAPI_NETWORK_COMP_ADD in the program to upload materials to various network activities from an excel sheet.

    Regards

    Srikrishna

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 18, 2009 at 05:58 AM

    Hi,

    Use the BOM transfer Functionality in SAP (TCode: CN33)

    This uses the reference points in the activities and the BOM Components to identify each other.

    Refer the Link below:

    http://help.sap.com/saphelp_erp60_sp/helpdata/en/d7/b8853488601e33e10000009b38f83b/frameset.htm

    Hope it helps...

    Thanks!!!

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2009 at 06:27 AM

    Dear,

    For big amount of material assigned to activity you need to create WBS BOM by CS71 and assign component here and add reference points to line items and same reference point to activity after transfering the BOM by CN33 material assigned to activities as per reference points.

    Regards.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2009 at 06:53 AM

    Hi,

    Can use BAPI_NETWORK_COMP_ADD. It Adds multiple componets in a single call.

    Thanks

    Saikishore.Ganga

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 18, 2009 at 09:04 AM

    can also create standard network templates with assigned material components to activity

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 18, 2009 at 09:42 AM

    Hi,

    If you have excel sheet for materials against activities then you can take help of ABAP.

    Regards!

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.