Material planning currency in assignment tab of Internal activity

Former Member
0 Kudos

Hello Friends,

In the network configuration profile using OPUU, I have included material cost element in the activity parameter tab of internally y processed activity having control key PS01.

The inclusion of cost element as above will allow user to plan material value in the assignment tab of the internally processed tab. However, the currency displayed for planning is USD and that too is grayed i.e. non editable. Necessary screen shot is appended.

Can we change this default currency to object currency? Our is a global system in which is controlling area currency is USD but object currency is country specific i.e. for India INR, for SG the same is SGD, for Thailand it is THB etc.

Thanks and best regards

Accepted Solutions (1)

Accepted Solutions (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Standard SAP Functionality:

Amount of forecast material costs, in controlling area currency.

Hope it helps...

Thanks!!!

Former Member
0 Kudos

Hello

Thanks for your feedback.

Can you provide authentic SAP documents to estabilish your argument ?

That will be very helpful to me.

Thanks once again and best regards

Bharat Parikh

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Press F1 on the field, material planning in the assignment tab of the Internal activity.

The very first line clearly mentions that.

Hope it helps...

Thanks!!!