Delivery date in MTO scenario

Hi all,

i'm working in a MTO production scenario and we are implementing SAP, but for me is very difficult to get how SAP can propose a delivery date. When a new orders came in, the MRP check materials and so on, and then ? How SAP can check the machines workload ? When a new orders with early delivery date came in , what's happen ?

Thanks

P.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Oct 02, 2018 at 01:31 PM

    Hi Paolo

    In this case, you should use ATO (assembly-to-order) instead of MTO. With ATO, system generates a production order for the finished product when creating a sales order and you can run a capacity availability check at this point, in order to check the machines capacity.

    Regards,
    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.