on 09-16-2009 10:03 AM
Hi Experts,
Now, our system is setting the components scheduling aligned with activity start date as default ( Components , General data tab , indicator : Algn. startdate.Comp )
Is that possible to set the default on Align. finish date ? and how ?
Thanks and Regards
Shubin
Goto OPUU..select your network profile...then check the "Align Finish date" box..now the components will be aligned to finish date of an activity