I have selected for A,B,C activities with the FS relationships. When I change the Earliest Start Date of the project the subsequent activity dates also have to shift automatically. That is not happening now. How to do it?
Thanks
Bekele
OK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
After change the dates do the schduling in the planning board
Select the /Project/WBS Edit ---> Functions ---> Schedule
Even still the same issue continue then check the project profile setting in OPSA
Plg/Board/dates tab page
check the With activitites check box
Thanks
S.Murali
Edited by: S.Murali on Sep 16, 2009 12:16 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.