Project Planning Board

Hi!

I have selected for A,B,C activities with the FS relationships. When I change the Earliest Start Date of the project the subsequent activity dates also have to shift automatically. That is not happening now. How to do it?

Thanks

Bekele

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 16, 2009 at 06:41 AM

    Hi

    After change the dates do the schduling in the planning board

    Select the /Project/WBS Edit ---> Functions ---> Schedule

    Even still the same issue continue then check the project profile setting in OPSA

    Plg/Board/dates tab page

    check the With activitites check box

    Thanks

    S.Murali