cancel
Showing results for 
Search instead for 
Did you mean: 

Project Planning Board

MohanDesai
Active Participant
0 Kudos

Hi!

I have selected for A,B,C activities with the FS relationships. When I change the Earliest Start Date of the project the subsequent activity dates also have to shift automatically. That is not happening now. How to do it?

Thanks

Bekele

Accepted Solutions (0)

Answers (2)

Answers (2)

MohanDesai
Active Participant
0 Kudos

OK

Former Member
0 Kudos

Hi

After change the dates do the schduling in the planning board

Select the /Project/WBS Edit ---> Functions ---> Schedule

Even still the same issue continue then check the project profile setting in OPSA

Plg/Board/dates tab page

check the With activitites check box

Thanks

S.Murali

Edited by: S.Murali on Sep 16, 2009 12:16 PM

MohanDesai
Active Participant
0 Kudos

Hi! Murali,

I don't change the earliest start date anywhere. When I move the activity A to a new position on the Project Planning board Gantt Chart, automatically subsequent activities dates have to change. Is it possible?

Regards,

Bekele

Former Member
0 Kudos

Hi

No it is not possible automatically immedeatly after the movement of the activity.

Move the activity in gantt chart and then select the WBS and do the scheduling .

The subsequent activities will move automatically after the scheduling.

Thanks

S.Murali

Former Member
0 Kudos

This message was moderated.