on 09-12-2009 3:26 AM
hi experts,
When I copy a project from another operative project with list of material (external), the plant (in the material component) tab is also copied over to the new project. Is there any way that I could change this plant assignment for each material - it is greyed out in my system.
Additional information:
1. All of these material are Non-Stock (so Plant is irrelevant)
2. Procurement type = third party procurement (PFS)
Thanks, Tony
Hi
It is not possible to change the plant while copying or with mass change function.
Alternatively you can copy all the WBS elements and activities without materials. Set a subsitiution rule to change the Plant at network level.
Regards
Srikrishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.