Copy Project and Mass Change

Former Member
0 Kudos

hi experts,

When I copy a project from another operative project with list of material (external), the plant (in the material component) tab is also copied over to the new project. Is there any way that I could change this plant assignment for each material - it is greyed out in my system.

Additional information:

1. All of these material are Non-Stock (so Plant is irrelevant)

2. Procurement type = third party procurement (PFS)

Thanks, Tony

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

It is not possible to change the plant while copying or with mass change function.

Alternatively you can copy all the WBS elements and activities without materials. Set a subsitiution rule to change the Plant at network level.

Regards

Srikrishna

Former Member
0 Kudos

Thanks Srikrisna, have you used this substitution rule to change the plant at network level? do you have example on how you set your substitution rule?