link between Delivery schedule line counter from PO and the material docume

Dear Gurus,

I have one PO with single line item having delivery schedule -


Material 1 -


delivery schedule 01.01.2009 2000

01.03.2009 5000

I have received quantity against this Po

I want to know where I can find the link between Delivery schedule line counter from PO and the material document

Best regards

Sar

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Sep 11, 2009 at 07:08 PM

    There is no link from the MAterial document line item (Table Mseg) to the PO Schedule Line (EKET).

    If this is for Evaluating an on time delivery or GR, you may consider the following approach.

    PO details Po Date QTY

    Sch1 01Jun2009 200

    SCH2 08Jun2009 100

    GR Details

    GR1 01Jun2009 180

    GR2 07Jun2009 110

    GR3 09Jun2009 10

    Calculate a cum total qty for the PO Line.

    PO details Po Date CUMUL QTY

    Sch1 01Jun2009 200

    SCH2 08Jun2009 300

    Calculate a cum total qty for the ontime GR.

    PO details Po Date CUMUL PO QTY CUMUL GR on time

    Sch1 01Jun2009 200 180

    SCH2 08Jun2009 300 290 (180+110) the 3rd GR was too late

    Evaluate the PO SChedule Lines as follows:

    Po SCL qty + CUMUL GR QTY - CUMUL PO QTY = ADJ GR ON Time Qty

    SCH1 01Jun2009

    200 + 180 - 200 = 180 on time for 01Jun2009 date ( 90% fill rate)

    SCH2 08Jun2009

    100 + 290 - 300 = 90 on time for 08Jun2009 date (90 % fill rate) the first 20 of the GR on 07Jun2009 went to fill the late, early date.

    Best of luck !

    SCH2 100 +290 - 300 = 90 on time for 07Jun2009 date

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 02, 2009 at 07:20 AM

    t

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.