re-scheduling the production orders

32 Views

Hi, say, our all machines were fully loaded with work, 100% capacity utilization for this year. due to break down maintenance, one machine is out of service for 1 day. accordingly those orders or operations that are scheduled need to shift to next day. so accordingly all the orders need to be shifted forward. is there any option to shift or re-schedule all the orders one day or for ceratain period? pls also advise after mrp run, aftr generation of planned orders, can we able to see the required capacity in cm01?