Hello,

I have posted Settlement document and in the background created Service PO and SES. I have also created ABD documents. Also I have released the ABD document to accounting and also created the incoming invoice . Now i want to cancel the ABD document but the confirmation status says "cost distribution cancellation failed " and life cycle status is "Cancellation Requested". How do i cancel this ABD document.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Sep 27, 2018 at 01:56 PM

    Do you mean you edited the Freight Settlement Doc and clicked the "Reverse Document" button? This sends a cancellation request from TM to ECC...

    Can you check for an associated XML error in ECC?

    In SXMB_MONI, you can look for the XML in error with type TransportationOrderSUITEInvoicingPreparationCancellationRequest_In. Or you can also check t-code /SAPPO/PPO2.

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Sarah,

      thanks. I got the solution . Basically i wanted to cancel the Agency business document through TM. So we just reversed all the predecessor documents and now it is working and we see that the ABD are cancelled. Thanks for your inputs though.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.