Sep 10, 2009 at 09:47 AM

Capacity Requirements not generated in REM

122 Views

Hi,

I am using REM. I have created scheduling paramaetrs for planned order. I have selected the Generate capacity requirements in the scheduling parameters for Rate based scheduling.

In the work center, I have selected the Relevent for finite scheduling.

When I check the Capacity evaluation, there are no capacity requirements generated even though there are planned orders created by MRP.

Thanks and regards

Murugesan