on 09-10-2009 8:27 AM
Hi!!
I would like to ask for your help..
I have to change frequently procurement type in material master (view "MRP 2")
How can I, afterwards, refresh the BOM linked to that material, so to have new procurement updated for my production order??
Thanks for your kind answer!!!
Regards
Chiara
Dear Chiara,
For the already existing production orders,after entering the order no in CO02,click on Functions--->Read PP Master Data,so
that the made changes become effective.
For the change which you have made can be seen during the next MRP run in the system.
Check and revert back.
Regards
Mangalraj.S