cancel
Showing results for 
Search instead for 
Did you mean: 

Manual creation of planned orders

Former Member
0 Kudos

Hi,

Please gv me knowledge on the folllowing points

1.Can planned orders be created manually.If so t.code pls

2.Can one planned order have more than one production order with different batch number

3.In what report we can see all the production orders for any given planned order

Thanks and regards'

GVRR

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

1 Yes T code MD11

2 CO40 to create Production order from plan order, but it is not possible to create more than one PO

3 After conversion from plan to Production ,you will get get refrence of plan oder in Production order(Assignment tab)

regards,

Girish

Former Member
0 Kudos

Thanks Girish & others

gvrr

dhaval_choksi3
Active Contributor
0 Kudos

Dear Friend,

CO40 to create Production order from plan order, but it is not possible to create more than one PO

Before closing thread, have you check whether above answer is correct or not????

Regards,

Dhaval

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

1)MD11:mANUAL CREATION OF PALNNED ORDER

2)Yes you can. You convert planned order to production order partially. EG you have planned order for 100.Convert it production order partially i.e say qty10.One prod order will be generated. aGain you convert to production order from the same planned order.other prod order will be genearted

3)Once planned order is converted to prod order, planned order does not exists.

Regards,

satyajit

dhaval_choksi3
Active Contributor
0 Kudos

Hi,

Yes Plan order can be create manually too.

T.Code is md11

You can have more then one production order for 1 plan order.

You can create using it T.Code CO40(select option of partial Conversion)

Now regarding checking plan order no of any production order you need to check it manually in assignment tab of each production order.

Regards,

Dhaval

former_member225891
Participant
0 Kudos

Hi,

U can create planned orders manually t-code is MD11

and abt one planned order to multi production order i dont think so it will happen but wait for experts reply

Regards,

Karad D D