on 09-09-2009 1:12 PM
Hello Gurus,
My clients are using project systems for project costing. Their requirement is to maintain the Activity Plan Prices for the next 5 yrs. This is so because if they plan for a prospective project that may carryover to next year, they need to find the cost of the project.
I have the following questions in this regard:-
1) I set the plan activity price of an activity at Rs 50 today for next year and start costing for a project, suppose next year I feel the prices need to be changed to Rs 55 and I am at period 4 of next year.
Now, if I change the activity price at period 4 will the plan prices input into that project for period 1,2 and 3 will also be suitably updated?
2) Is there any chance of any data inconsistency at any point?
would be nice to get you views on this issue.
I f activity prices change in KP26 no effect will take place in project costing (old values are used).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi once more...
i performed the test in our system...
cj40 project costing with activity types
kp26 change activity price for the cost center used in cj40
cj40 examine the cost->no change occurs unless we make a significant change to project costing (ex erase the number of hours and write them once more). It was only at that time the system managed to re-read the new activity prices of kp26.
What do you think? Your business needs are different?
Pan
User | Count |
---|---|
94 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.