Hi All,
We are using SRM 3.0, EBP 4.0 ECS and R/3 4.6C.
I have posted confirmations for a Service PO successfully in SRM and a GR and Service Entry Sheet has been posted in R/3 correspondingly. However some of the confirmation results in the status "Currently being transferred" and R/3 does not get updated with GR and Service Entry Sheet.
I have checked that the workflow has processed succesfully and it is in 'Completed" status.
Our observation - While posting cofirmation for a Goods PO, the GR is posted in R/3 using IDOC. We can trace the same in transaction WE02. While posting confirmation for a Service PO, GR and Service Entry Sheet is posted in R/3, however not sure how this is posted as we are not able to trace any IDOC for a Service PO confirmation.
I need to know how confirmation is posted for a Service PO.
Any pointers to resolve the above issue would be highly appreciated.
Thanks in advance,
Francis
Hi Serguei,
Thanks for the reply.
Have gone through the links that you have sent. Were informatory.
Will let you know if we will be able to solve this issue.
Regards,
Francis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Even for service PO confirmation IDOC is generated and posted in backend. You can use t-code WE09 to find out particular IDOC based on search value.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sachin,
Thanks for your response.
I have checked in WE09 as well, there are no IDOC's posted for Service PO's.
Found out that the confirmation for a Service PO is posted via RFC. But have not been able to trace the RFC failure in RZ20 or SM58 as well.
Any pointers will be appreciated.