Dear all,

I have stuck in to one scenario which is as fallows are in to chocolate production company with discrete manufacturing where the chocolate have many stages to become finish. Now there is one stage where the chocolate is been wrapped by nearly 50 to 60u2026 employees. my quire is that what should I treat these employees work centersu2026? and if work center how can I maintain there capacity as one employ will wrap 50 chocolates in an hour and other will wrap 70 and there is no fix employee for these processes today there will be one different employee and tomorrow there will be some another employee. And how can I maintain there capacity as it fluctuates...

I will be highly obliged if one cane help me to map this scenario in sap pp