How to copy budget to planned/forecast version ?

Former Member
0 Kudos

I need to copy an actual budget (CJ30) on a planned version (CJ40).

How can I do that ??

Hope somebody can help...

Sandrine

Accepted Solutions (1)

Accepted Solutions (1)

iklovski
Active Contributor
0 Kudos

Hi,

The opposite it possible (copy plan to budget), but not vice versa.

Regards,

Eli

Answers (1)

Answers (1)

Former Member
0 Kudos

Thanks for the (bad) news,

I hope I will find another solution...

Sandrine