POC actual aggregate

Dear All,

I have this situation where when I do the confirmation for activity elements within an activity, due to a fractional progress, the values for Actual POC percentage are coming too small. For example the Work for an activity element is 100000 m3 and while confirmation, i enter actual work as 150 m3, the POC comes as (150/100000 * 100 = 0.15%).

In this case when I run CNE5, system gives a warning as "You have selected different units for calculation the work and the duration.

In this case, the calculated value of work would be very small. Since the field only allows one position after the period, the system represents this value with 0.0. However, this would be misleading because there actually is work"

Due to this, the system is not rolling up the POC actual aggregate to the top.

Please help.

Regards,

VikasD

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Sep 09, 2009 at 10:59 AM

    Hi,

    Go to Tcode: OPTU

    Select : SAPPS_EV0001 or as per your selection criteria.

    The last column has Decimals. Please mention the number of decimals you would like to see.

    Hope it helps...

    Thanks!!!

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.