on 09-09-2009 10:39 AM
Hi All,
does any std report is available to show the material shortage for the requirement which creaed by the last mrp run.r
Dear Raj,
after MRP run , just check in MDVP for AV check at plan order level
Regards
kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
CONGRATS DEAR . R.BRAHMANKAR.
I need the report like list of material with the shortage of quantity for the whole requirement. not in terms of planned order.
this is rem process.
more as a ex : if i reqmt is (ind reqmt + dep reqmt) 100
avail stock is 50
so the stoage is 50 it show.
which table i need to check
Hi ,
I think you have to go for a Z report to have a material shortage details.we have met the same type of requirement by using the Functional module MD_STOCK_REQUIREMENTS_LIST_API.
Here you will get the the detialis like you get in MD04 (required qty -available qty=material shortage),form which you can meet your requirement.just sit with your ABAPER and explain theis functional module.
Hope it helps
The Pull List (MF63) & the staging report MF60 should help you if you work with REM...Did u try that??
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.