The Time Management Scenario : Need Suggestions :

There are two persomnal areas: A and B

Personal Sub Areas For A: 17 regoinal offices which work

All the Regions Have Same work schedule ,Breaks and off's.

but one of the region they have marketing and normal administrative prople

marketing people : 6 days working and sunday off

: they have half an hour unpaid leave

: 8:30 to 6:30

Administrative People : 5 days working and sat and sun off

: they have half an hour unpaid leave

: 8:30 to 6:30

now B has two personnel sub areas :

B1 : 5 days working and saturday as half day

: they have half and hour unpaid leave

: 9:30 to 6:00

B2 : 6 days working

: they have half and hour unpaid leave

: 8:30 to 6:00

now tell me how to go ahead for time management daily work schedule groupings.