Scenario:

Material = X

Material type = KMAT

Strategy Group = 20

For Material X, quotations are created before actual sales order creation.

These quotations particapte in MRP run and trigger material planning.

The need is : Quotations should not participate in MRP planning.

Thanks

Nitin

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Sep 09, 2009 at 05:58 AM

    For Item category for Quotation, assign the Schedule line categiry = "No MRP"

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.