Hi All

After MRP run, purchase requisition is generating on per material basis. I mean if i am running MRP run for 1000 material in a plant. 1000 PRs are getting generating.

Can i combine the article in any way so that i can generate single PR for a number of materials? I would like to maintain some parameter in material master for particular plant, so that when i run the MRP for that plant, based on that parameter, single PR can be generated for multiple materials.

e.g. can i generate single PR for 10 articles which is supplied by single vendor. Don't want to generate 10 PRs.

Please confirm.

Thanks & Regards

Kapil Nanda