WBS Element Group

Hi,

What is the procedure to create WBS element group ?

Thanks!

Harsh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Sep 08, 2009 at 06:29 AM

    Hi,

    ohk

    i created using CJSG but how to remove it?

    is their any report where i can see assigned plan cost to the group created by cjsg?

    thanks!

    Edited by: Harsh Saxena on Sep 8, 2009 12:01 PM

    Edited by: Harsh Saxena on Sep 8, 2009 12:09 PM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 08, 2009 at 04:42 AM

    Dear,

    WBS element grouping is used for material requirement grouping to group material procurement from various WBSE.

    All requirement will consider as group of wbs element.

    Refer this link for detail

    http://help.sap.com/erp2005_ehp_02/helpdata/en/d7/b8853488601e33e10000009b38f83b/frameset.htm

    http://help.sap.com/saphelp_dimp50/helpdata/EN/d3/a51129e32311d1a6ab0000e83235d4/content.htm

    Regards.

    Edited by: Sukhveer Singh on Sep 8, 2009 6:43 AM

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear,

      WBS element group

      A WBS element group is a combination of a number of WBS elements which

      may originate from different projects. WBS groups do not contain

      hierarchy information.

      Such groups are useful, for example, if you want to plan the WBS

      elements of a particular project manager jointly.

      Go to CJSG and you can generate the cost element group from there and make cange or add other wbs element alsso.

      Regards.