Runtime for heuristics and Deployment

Hello All,

When I execute the Heuristics or Deployment (SCM 7.0) even for a single product it takes around 15 minutes.

So let me know how to improve the run time.

Or do we need to install any support packages?

Thanks,

Siva.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Sep 11, 2009 at 11:11 AM

    Dear Sive,

    please check whether notes 1320583, 1356099, 1283261, 1140057 and 1279844 are relevant for your system.

    Regards,

    Tibor

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 08, 2009 at 05:40 AM

    Hi Siva,

    The run time is too long and reason might be the Live cache space.

    Try to increase the live cache memory or clear the live cache data. For increased run time the data load in live cache should be less. You can clear the live cache data by taking its backup.

    Run time is directly proportional to live cache performence so you need to optimize the peroformence of live cache. Ask to basis guy to check the stcked tables and clear it.

    Regards,

    Santosh

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 08, 2009 at 06:06 AM

    Hi Siva,

    Check the following

    1) Any master data error in the location product planned (MRP views, resource used, PPM, lane, material master etc.,)

    2) Check the job log in sm37, if no log created, delete the job and rerun again

    3) Check inbound and outbound queues

    4) Check the application log if any errors displayed

    5) Run CCR for the location product for all transactional data and then run heuristic

    Confirm your observations.

    Regards

    R. Senthil Mareeswaran.