md51 not working

Former Member
0 Kudos

hi experts,

i created wbs bom,and transfered it to activity by t-code cn33,the material be assigned to activity successfully,after i relased the project,i ran md51 to get planned order,but Materials planned no values i got,i am not similar with pp,if some steps for mrp should i configure

best regards

zlf

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

What is the procurement indicator you have used? MD51 will generate requirements like PR / Planned Order only when you use Reservation for WBS...If you have used Reservation for Networks MD51 will not work. So check it.

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Dear,

in OPS8 you can make it.

or in the control data tab do't tick any of three column.

Sukhveer.

former_member203108
Active Contributor
0 Kudos

This message was moderated.

Former Member
0 Kudos

thanks all

best regards

zlf

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear,

Maintain MRP view in ,material or material is not relevant for MRP.

Regards.

Former Member
0 Kudos

hi,

material is relevant for MRP,and mrp1/mrp2/mrp3/mrp4 views already exsits,in mrp2 the purchase type is 'E',any other suggestions?

best regards

zlf

Former Member
0 Kudos

Dear,

1. What is the MRP type of the components? "PD"?

2. What is the special procurment key of the components (in material master and BOM)?

3. Are the componentsw ritten as stock items "L" in the BOM?

or check the stock is there or not?

Regards.

Edited by: Sukhveer Singh on Sep 8, 2009 7:31 AM

Former Member
0 Kudos

hi Sukhveer Singh

the MRP type is 'PD'

the special procurment key is null

components as stock items are all "L"

best regards

zlf

Former Member
0 Kudos

Hi,

Check MRP strategy in Material Master.

Regards,

Nitin