Skip to Content
author's profile photo Former Member
Former Member

Plan driven open PR quantity

Hi All,

I've got the following scenario in PDP (SRM extended classic scenario):

1. PR created in backend with quantity 10 unit

2. Run program bbp_extreq_transfer in backend to transfer the PR

3. SC created in SRM with quantity 10

4. Change PR quantity to 15 unit in backend

5. Run program bbp_extreq_transfer in backend to transfer the PR change

6. Neither new SC created nor quantity change happen in SRM

What the setting required in order to cater the balance of 5 unit in SRM?

Thanks.

Has.

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Sep 05, 2009 at 11:04 AM

    As per the standard it should update the SC with the changed qty.

    1) Please check SMQ1 in ECC and SLG1 in SRM to analyse ths issue.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      There is no error in SMQ1 or SLG1. When I checked in txn BBP_PD, the SC was changed but only date/time of last changed field. Quantity remain as the same. Fyi, the SC status is approved (auto).

  • Posted on Sep 08, 2009 at 06:33 AM

    hi,

    Please check whether the PR is blocked,. Release the P.R

    Then run the program. Thq qty will be transferred to SRM

    Regards

    G.Ganesh Kumar

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 08, 2009 at 07:37 AM

    Hi

    It ios paln driven procurement

    Already you have pushed PR to SRM and it created SC w.r.t PR.

    now why do you want to change the requirement from 10 to 5?

    i dont think so it is not possible.

    generally your system should not allow to edit the quantity field. but i do not know how you are enjoying by editing the qty field int he PR.

    br

    muthu

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 09, 2009 at 03:53 PM

    Hi Has,

    It's either (a) incorrect configuration or (b) system bug. The updated quantity should be displayed in SRM.

    For (a), check your Entry Channel - Company relationship in your Org Structure. Refer to this thread for a similar issue:

    [Error updating external requirements in SRM|https://forums.sdn.sap.com/click.jspa?searchID=31445050&messageID=5717280]

    If you're sure your configuration is correct, raise an OSS message for (b).

    Cheers,

    Serguei

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.