Change PR details in PO creation

Former Member
0 Kudos

Hi,

When we are creating a PO that originates from a PR, it doesnt allow us to edit the Account assignment anymore. Is it possible for us to still edit the accoung assignment after adopting the PR in PO creation?

thanks,

Paula

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI Paula ,

It's possible to change in PO.

Check the screen layout against field selection AKTV.

SproMaterials ManagementPurchasingPurchase OrderDefine Screen Layout at Document Level

Regards

Ramesh Ch

Answers (1)

Answers (1)

Former Member
0 Kudos

Hey

Is your PR flow into release procedure?

then check the release indicator settings

Regards,

Raman