Hi Experts,
This is really question for experts.
In legacy, User confirm the start time and end time of the work center.Here the issue is when user starts machine he press START button and when they finish they press STOP button. Legacy capture the start and finish timings for each work center through this process. User wants same process in the SAP also.
How do we map in SAP.Is there any standard SAP or Zprogram.If Z program need how do we develop.can any one help.Thanks in advance.
Bye.
Ravi.M
Dear Ravi,
As per my knowledge
ur scenario can be mapped as time event confirmation
t-code for time event confirmation is CO19
here start , finish etc can be entered time to time
Regards
kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.