Dear All ,
We are using CM01 for capacity Planning .
Here it is showing capcity occupied by Planned orders .
In CM01 can i convert Planned order to Prd ord ? If yes , How ?
Pl guide
Regards
Dear,
As per my concern it is not possible to convert planned order to production order in CM01.
You can use the CO41 or CO40.
Regards,
R.Brahmankar