on 09-03-2009 9:34 AM
Dear Gurus,
When I run Cost estimate with quantity structure in CK11N for an semifinished assy, I am getting the below error for the activities.
********************
No structure could be determined for internal activity LABOR (COSTCENTER)
Message no. CK694
Diagnosis
The system could not determine a cost component split for the internal activity with activity type LABOR of cost center COSTCENTER.
Procedure
Check the master data for activity type LABOR of cost center COSTCENTER. It is possible that no activity price calculation has been carried out for the cost center.
*******************
Please advise me.
thanks and regards
Murugesan
Hi,
Check in KP26 whether you have fixed price for LABOR for the cost center. Further, check the cost component structure in OKTZ
whether the cost element for labour has been assigned.
Regards,
Sadashivan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Could you please check the OSS note "SAP Note 1872228 - No Cost Component Split in Plan Price Calculation". I have also faced the same issues and it get solved by implementing this oss note.
Before implementing this oss note, check whether KP26, KP06, Cost component structure are OK. Then execute the process KSS4 for Plan cost split and then KSPI.
Then check the report S_ALR_87013644, whether the cost component split is working or not. If not then implement the oss note 1872228.
Thanks
Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Would you please let me know how you solve this problem at last? As we have the same problem as yours.
Thanks in advance
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Murugesan,
Use T. code KEI2 and check that PA structure for LABOR is properly maintained or not if not maintain the same properly accordingly, also check that created Activity Type is assigned to the material BOM because the cost center assigned to the corresponding work center helps to calculate the unit cost for the product costing.
Regards,
Shailesh Verma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.