on 09-01-2009 7:33 AM
Dear SAP Gurus,
While doing costing run the system is throwing an error as "Cost component split costed with value of zero".
Please suggest any some solutions
Edited by: KCPTECH on Sep 3, 2009 7:27 AM
HI
System Throws this message when the cost of any component coming in standard cost estimate is zero. Check yoy costing lot size,Try temporarily increasing your costing lot size by a hundred or a thousand times. This should enable you to run the cost and allow you to examine further.
Plz check this thread
Regards
Anupam Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to Cost component Structure,
Select ur Cost component , If not Create,
Click on Cost component Attribute, (Create attributes with sum code for Raw materials, Semifinished, Chemicals, Activiity , OVHD)
Again ,Select Each Attribute, Give the Consumption G/L'swith respect as r/w,semi,etc in each line items.
Consumptions include all the materials G/L for the materials in BOM,
This may solve ur problem.
Regards,
Pavanidlur
Hi,
Check CK11N is BOM is picked up in costing run.
Have you maintained alternate BOM??
Regards,
Vishal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.