Hi, we want two inspections at the same stage of reciving / manufacturing, say, during receiving we want one inspection by our internal team and another inspection by third party. i have enetred 01 in qm view of mat master. while enetring secone time (01), it is giving the meassage that insp type is already exists. pls advise how to handle this.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can not activate same inspection type twice in a material master.

also remeber you can not create two lots for same inspection type.

Here you have to use either different inspection type or manual lot with same inspection type 01.

1.One solution cen be use 103-105 mvt types.

during 103 you can create a manual lot of 01.(by internal team)

then do 105 which will trigger 01 inspection lot Automatically.(External team/third party)

2.Use 101 mvt type.01 inspec lot will create( .(by internal team).Post this to say X storage location.

Now activate 08 inspection type for material.Using MB1B -->311 mvt type move material from X to Y storage Location.

08 inspection lot will be created.(External team/third party)

Regards

Sujit

Answers (2)

Answers (2)

Former Member
0 Kudos

Hii,

Activating same inspection type twice is not possible in material master. ur point is u hav to record results by internal team and third party. For one inspection lot if u want to do RR, then U can define two operation in the inspection plan first operation for internal team and second opeartion for third party results. Then u can define repective mic for each operation and carryout RR.

regards,

K.Lokesh.

tanuj_parikh
Active Participant
0 Kudos

Hi,

This you can handle by creating Manual Inspection Lot (where you can't post stock) in addition to normal '01' Inspection Lot.

OR

Create Inspection Plan with duplicate MIC for which two different Inspector can record results for their respective MIC.

OR

In RR screen itself, you can have control like Chemist is recording (Entering) Result only and Executive is valuating (Status=3) that result and on completion of RR for all operation and MIC, Head is giving UD (this can be controlled by Authorization).

Regards,

Tanuj Parikh