on 08-29-2009 10:46 AM
Dear All ,
Pl guide for the following :
Depending upon the Costing Overhead Grp the Overhead will be applied , in our case Overhead % applied depending upon the Raw material consumption . So we have incorporated Over head key in all Semifinished material .
Here , in all assembly all HALB material have Over head Key ,
but whether we should have Overhead Key to Finished material also?
Rgds
Hi Venky,
No It will pick up from Halb code ifself during Fert code explosion during standard cost estimate.
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Venky,
Not clear.
Have you maintain overhead group both in Halb and ROH both.Or is it only in Halb?
It should be like this,
ROH contains Origin Grp ---> Halb code contains ROH ---> That Halb code contains over head grp ---> Fert code containes Halb.According to this sequence Overhead grp and origin grp pick during the std. cost estimate and order costing.
If you have maintain overhead grp in both then I afraid your overhead cost will calculate doubel.
And if overhead grp is maintain in halb only then raw material consumed in Fert directly will not effect on overhead cost.
For better clarity check it at your end.
Regards,
Dhaval
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.