on 08-29-2009 9:17 AM
Dear all,
when we get NTUP staus in PRD order (dates not updated)
where will it effect if we have this status in PRD order
Regards
kumar
Dear,
In the production scheduling profile in the Customizing (Transaction OPKP) it is defined that the order shall be scheduled in case of release.
Furthermore it is defined in the check control for the availability check in the Customizing (Transaction OPJK) that in case of order release at least one availability check shall be executed.
the order is scheduled again in spite of that
the operation dates of the rescheduling are adjusted, the dates of the order header however not. Through that status NTUP sits in spite of the executed scheduling (Dates not current) for the order.
Other case Check whether the network header can be assigned later to a WBS element so that the 'NTUP' status is set when this
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi kumar,
The confirmation dates or the scheduling dates are not updating in the order. Check the parameters in transaction OPK4-confirmation parameters and in OPL8-Order type dependent parameters.
thanks and regards
Murugesan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Murugesan,
Thanks for ur prompt reply
confirmation has not been taken place
just order has been created & relesed
and i can see this status
anyways got it solved
it was costing effect
there was no costing run for this material
so it was showing the status NTUP
after taking costing run CK11N
then it was ok
Regards
kumar