on 08-28-2009 6:51 PM
Dear Experts,
As i understood that planning sequence will always read all the data from
the cube and will be processed as per the planning function we select.
Then won't this duplicate the data as the same data is being read every time
planning sequence is run along with the new data, if yes how this is being handled.
Is their any underlying functionality which is working so the planning sequence
will not process already processed data (like delta mechanism in regular BI)
Can somebody give me some step to step understanding of the imp planning functions available
along with some example scenarios.
Thanks and Regards
Neel
Hi,
you should ask this question in the planning forum.
In generell reading the data is done via the OLAP. This BI-IP uses the same technology as standard queries (include caching). Changes values are stored seperatly in the planning buffer (and delta buffer).
So you see plannig function/sequences do not read all the data from the database all the time, but use buffering mechanism intensively.
Hope this helps ...
Regards Matthias Nutt
SAP Consulting Switzerland
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
76 | |
10 | |
8 | |
8 | |
6 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.