Sir,
WE have two plants.Plant A & B.
Plant Ais the planning Plant.B is the production plant.
For plantA finished ProductA---->product B
In
Plant B,
Product B------> Product C & D
Product B-------> Product D& E
I have maintained quota arrangement in Plant B for product B.
If i run for Plant B.After Mrp, quota arrangement is good.
Suppose I have run for Plant A ,so I have to produce product B in Plant B.Because I have maintained special procurement key.
But I got plannd order for Product B inPlant B.But quota arrangement is not working.
How to make quota arrangement.
bhuvan