Dear all,

say i have BOM of five levels (multi level BOM)

now i have five Production orders for each level

in Routing for each level i have only one operation

all components are assign to first i.e 10th operation in each order

so for all levels of BOM, correspoding Routing will be having only one operation

Now the query is should i go for CO15 confirmation or CO11N confirmation

which will be the best, to suggest

Kindly share ur views

Regards

kumar