Hello Everyone,
In my project an enhancement been done for running Route Determination at the time of PO save. In order to update GR time in MD04, I am updating field TERMN in EKET table at the time of PO save that finally reflect in MD04 when MRP is run on that material. But the problem is when this is not happening in one PO, It updated TERMN at PO schedule line level but when MRP is run it shows delivery date without considering GR processing time.
is there any condition when GR time not considered when Route is run.
Is there something i need to check to find the cause.
Thanks
Sunil