on 08-27-2009 8:33 PM
I created a production order, released it, and then made changes to the BOM. I went back into the production order and did Functions > Read PP master data. The system gives the message "error when checking BOM - reading routing without BOM not possible after release".
I have deleted all relevant (1) inspection lots (2) transfer reqs. No transfer orders exist and no material movements appear to have been executed.
What am I missing? Why won't the system read the BOM?
Thanks much!
Sarah
Hi,
Please check the relevancy in OS30 and OPL8
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Cancel any Inspection Lot generated, reverse the confirmation done and try again.
Regards,
Tanuj Parikh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sarah,
As simple suggestion would be to check the Logs which were created when Read PP Master data functionality was used. From the menu GOTO->Logs-->Read PP Master Data, this would give you the reason as what has happened and why it is happening.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Please check validity date of BOM and order start and finish date of production order.
Regards,
vidyasagar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.